Pontoon RFQ and Quote Comparison Template

AustraliaUpdated 11 September 2026

Marina basin seen from above, showing pontoon berths against the shorelineHelmutAschauer · CC BY-SA 4.0

Information to issue to every bidder

Buyer and project

  • project address/waterway
  • owner/entity
  • private/public/commercial
  • target completion
  • approval status

Vessel/equipment schedule

For every vessel or major machine provide:

  • type
  • LOA
  • beam
  • draft
  • displacement/full-load mass
  • projected windage if available
  • intended mooring arrangement
  • outboard/drive protrusions

For plant provide:

  • operating mass
  • centre of gravity
  • dynamic loads
  • vibration/torque
  • lift points
  • hose/pipe loads

Site information

  • water levels
  • depth
  • bed material
  • waves/wake
  • current
  • wind
  • flood
  • navigation envelope

Mandatory bidder response table

Item Bidder response
Pontoon dimensions
Frame material/alloy/grade
Float material/type
Deck material
Empty freeboard
Design loaded freeboard
Design live load
Concentrated load
Maximum intended persons
Restraint system
Pile/anchor design included?
Gangway size
Design standards
Site-specific engineering?
Engineering signatory
Approval service included?
Freight
Crane/barge
Installation
Electrical
Water
Warranty
Lead time
Exclusions
GST
Total contract price

Quote normalisation

When one quote includes engineering and another excludes it, add realistic allowances before ranking price. Use a comparison sheet with three values:

  • quoted
  • adjustment for excluded scope
  • normalised project cost

Procurement red flags

  • "built to Australian Standards" without identifying standards
  • no site-specific design basis
  • no stated load or freeboard
  • no responsibility for pile/anchor design
  • very small deposit followed by a very large pre-delivery payment with no inspection right
  • no drawings before manufacture
  • no written exclusions
  • no warranty document
  • no reference projects in similar exposure
  • no discussion of approvals
  • builder refuses to disclose float/frame/deck material grades
  • engineering certificate offered only after extra payment despite being represented as compliant